Ola Electric gets notice for missing battery 'gigafactory' setup deadline

Ola Electric gets notice for missing battery 'gigafactory' setup deadline

A man walks past the logo of Ola Electric during a press conference ahead of it's IPO launch in Mumbai, India, July 29, 2024. REUTERS/Francis Mascarenhas/ File Photo

Indian electric two-wheeler maker Ola Electric received a letter from the federal government on Tuesday for missing a key milestone in the setup of its planned battery “gigafactory”.

Ola was selected in 2022 for the government’s production-linked incentive (PLI) scheme to establish a 20 gigawatts (GW) local battery manufacturing facility in the southern state of Tamil Nadu.

The Rs 18,100 crore ($2.07 billion) scheme required companies to set up manufacturing facilities within two years. Ola Electric has previously said it would begin commercial operations at the manufacturing facility by April.

Its Tuesday statement said the company was actively engaged with relevant authorities, but did not offer details about the missed milestone or spell out what steps the government could take next.

Ola Electric has lost roughly 40% of its market value since going public last year, pressured by high costs, weak demand and deep discounts that have led to job cuts in its push for profitability.

Earlier in the day, Mukesh Ambani-led Reliance New Energy Solar Limited also received a similar letter from the federal government for missing its timeline to set up a manufacturing plant under the same scheme.

Reliance said its penalties stood at 31 million rupees ($355,293) as of March 3, and that it had asked the government for more time to set up its manufacturing plant.

It was not immediately clear how much Ola’s potential penalties would be.

Reuters

Bring stories like this into your inbox every day.

Sign up for our newsletter - The Daily Brief
Subscribe to Newsletter

This is your last free story for the month. Register to continue reading our content